SCOPE
Re-route of 2 overhead 138kV transmission lines and 7 overhead 69kV transmission lines through the multi-phase construction of the new 138kV substation.
PROJECT DESCRIPTION
The construction of the overall substation was carried out in 20 smaller phases through various constraints. ASEC coordinated with transmission, substation, underground design and construction teams for the design to accommodate safe construction of the substation relocation.