SCOPE
ASEC worked on our client’s PCS program where antenna additions throughout the client’s systems were modeled and towers analyzed for strength and capacity requirements for the additional loads per governing client standards, GO 95 code and ANSI/TIA-222 Structural standards.
PROJECT DESCRIPTION
Loads were generated using ASEC’s proprietary software using an overload factor of 1.5 on the original design loads. Tower member reinforcements were designed for the additional load as required and unloading procedures devised for the member replacements for a safe and reliable construction sequencing.