Compliance Program

Compliance Program

SCOPE The scope included an emergency replacement of pole Z28270 for compliance. 69kV Transmission (636 ACS/AW conductor), 12kV Distribution overhead (636 ACS/AW Conductor) and 12kV Distribution Underground (2/0 AL conductor) to be transferred to the new SW steel...
Request to Attach (R2A)

Request to Attach (R2A)

SCOPE The CNF project was a series of replacements and upgrades of five existing overhead transmission line circuits with six distribution circuits. The ultimate goal was to increase the reliability and safety of the existing facilities in the high Fire-Threat-Zone in...